Project Phases

The project “Definitive Solution for the Road Axis 4 - Amazonas: Duran Bridge - Wawico Bridge - Santa Maria de Nieva/Nuevo Siasme – Saramiriza Corridor” has an approximate duration of five years and eight months and is divided into four phases.

Phase 0: Organization and Installation
(24/05/2024 – 24/06/2024)

Phase 1: Project Profiles Review
(24/06/2024-02/05/2025)

Phase 2: Preparation of the Definitive Engineering Study and Environmental Impact Study and Archaeological Componen
(02/05/2025 -11/08/2026)

Phase 3: Construction and Supervision
(11/08/2026 -03/03/2030)